Tuesday, September 12, 2017



The foundation work continues with the termite treatment completed, the waterproofing completed and the insulation board being installed.

The plumbing drain system that will be below the lower level floor has been run.  The forms, plastic, mesh and rebar have been placed so that we can pour the lower level floor next week.  We are calling the lower level the Fireside Level because there will be a fireplace with windows over looking the lake.
                        

And finally we have dug a trench and laid the conduit for the permanent power and data cabling. 


The construction team tells us we are "Getting Out of the Ground"