Saturday, October 21, 2017

The roofing is ready for delivery, flooring has arrived, purchasing antique dressers for restroom vanities and 3 brides toured the Chapel site this week!! Whew, it has been busy!! One of the couples has booked and two other bookings are pending....can't wait for the Grand Opening April 28th!! Watch for some photo updates next week!!  Happy Wedding planning!!

Saturday, October 14, 2017

Doors & Windows

We are trying to stay ahead of the builder, so we have been picking out roofing materials, windows and doors. The front of the chapel will have double doors for the main entrance and will have 2 single doors on either side:  One for the bride ready room and one for the office.  Here is a picture of the style we have picked for the front doors.


Heading Skyward



Now that the sanctuary floor has been completed there is nowhere to go but up!  Thanks to the framers, who are a hard working bunch of guys, we are making good progress with the building.

                             

Over the last 10 days they have installed the walls and the roof trusses for the sanctuary level.  These pictures face south which will be the wall with the floor to ceiling windows.  The view is still as spectacular as ever.

 

The framers built this  scaffold to work from while they installed the roof trusses.  We brought the crane back in to provide the heavy lifting.  Here they are installing the first roof truss.

    

 Here are a couple of pictures looking south towards the lake.  We are starting to get a good perspective of the 30'x70' sanctuary area in the chapel. In the end the 3 roof system was installed without a hitch






Friday, October 13, 2017

Bride Ready Room



This is the look we are going for in the Bride Ready room's bathroom.  Although, our mirror will be an oval glass tilt mirror not brown wood and we will have white bead board below the chair-rail.  Getting ready to take several prospective couples on Chapel tours in the next couple of days....can't wait!!  The cookies will be waiting!!

Tuesday, October 3, 2017

Moving Right Along



Wow!  We've been having fun.  We brought in a crane to do some of the heavy lifting.

  

With the help of the crane the framers were able to put the vertical and horizontal 12"x12"x12'(+/-) beams into place.  We now have the Fireside level completely framed in.

                                
 The beams became the support structure for the floor trusses for the main sanctuary level.

                        

Once the trusses were in place the crew was able to lay the deck for the main sanctuary level.  These pictures were taken at 7:00pm from the floor of the sanctuary for those looking for a spectacular backdrop.